Project costs and job costing

Set a contract value, budget and labour rate, then see hours, stock and bills booked to the project through the record graph — broken down by cost code.

Updated 24 September 2026

A project's Costs tab shows what the work was sold for, what it was allowed to cost, and what it has actually cost — hours, materials and bills booked to it from across the workspace.

Availability
See money on a project
View Finances as well as access to the project
Set contract value, budget and labour rate
Manage Projects
Where
a project's Costs tab

Without Finance access, the tab says Money on this project is hidden — it needs the Finances permission.

Contract and budget#

Choose Edit under Contract and budget and set:

  • Contract value — what the work was sold for.
  • Budget — what it is allowed to cost.
  • Labour rate — the cost of an hour, used to cost logged time.

What is booked to the project#

Every hour, item and bill attached through the organization graph is added up:

CostComes from
LabourHours logged against the project in time tracking, multiplied by the labour rate
MaterialsStock moved to the project in Inventory, valued at item cost
Other costsBills in Finance booked to the project

Alongside, Invoiced shows what you have billed for the work.

The result#

  • Total cost — labour, materials and other costs together.
  • Margin — contract value less cost. At a loss when cost exceeds the contract value.
  • Budget variance — under budget or over budget.

Cost codes#

Cost codes break a project's cost down by kind of work — groundwork, electrical, design. Define them in Projects → Settings → Cost codes (Add a cost code and press Enter), then set a code on each cost booked to a project. The By cost code breakdown shows where the money went; anything without a code is Uncoded. Retiring a cost code keeps it on past costs.

Why this works across modules#

Job costing needs no special setup because hours, stock movements and bills are already linked to the project through Unobits' record links. The same approach works for a construction job, an agency retainer, an event or a manufacturing run. See Connected records.